PROJECT: «SECOND ASPARUHOV BRIDGE ON TWO LEVELS» OF THE “BSEZC“ NPA

PROJECT „SECOND ASPARUHOV BRIDGE – TWO-LEVEL STRUCTURE – VARNA“

PROJECT SUMMARY

The Black Sea Economic Zone Cluster (BSEZ Cluster) has developed and proposes a concept for the construction of a Second Asparuhov Bridge as a two-level structure, designed as a strategic transport, urban, and economic infrastructure project for the city of Varna.

The concept envisages the construction of a new bridge over Varna Lake along a corridor defined in the current Master Plan of Varna, aiming to provide a second independent transport connection between the northern and southern parts of the city. The project is designed as a long-term solution to reduce dependency on the existing Asparuhov Bridge and to ensure a functional alternative in case of major rehabilitation, emergency restrictions, or increasing traffic demand.

The BSEZ Cluster positions the bridge not only as an urban transport facility, but as part of a broader strategic development framework, including port logistics, industrial zones, connectivity to Hemus Motorway and Black Sea Motorway, and long-term regional economic growth.

In its initial concept, the project is structured as a two-level bridge, where one level serves urban traffic and the second level ensures efficient connection to national and motorway infrastructure. The core objective is to establish a resilient, redundant, and strategically sustainable transport system for Varna.

PROJECT STATUS AND EXPERT ASSESSMENT

The project is currently at a conceptual / pre-investment stage. The BSEZ Cluster has developed conceptual designs, visual materials, preliminary investment frameworks, expert analyses, and justification for potential European and blended financing.

On May 20, 2019, an institutional working meeting was held at the Ministry of Regional Development and Public Works, initiated by BSEZ Cluster, with participation of EU funding experts from Brussels. The project concept, analyses, and financing rationale were formally presented.

The initial framework estimates:

  • Implementation period: up to 6 years
  • Investment volume: approx. €0.7 billion (Phase I)
  • Total development: approx. €0.9 billion (two-level model)
  • Initial ROI estimate: above 5.5%

The project is proposed in two realistic scenarios:

  • Scenario I – Urban bridge (Phase I): €120–180 million
  • Scenario II – Full two-level development: €600–900 million

This phased approach avoids blocking the project with an overly ambitious initial scope and prioritizes the urgent need for a second urban connection.

PUBLIC VALUE AND CONTRIBUTION OF BSEZ CLUSTER

The BSEZ Cluster has played a key role in consistently positioning the second bridge as a strategic priority for Varna at urban, regional, and national level.

  • Development and public presentation of the concept
  • Alignment with the Varna Master Plan
  • Preparation of expert analyses and visualizations
  • Institutional engagement and coordination
  • EU-level presentation and dialogue
  • Raising awareness of Asparuhov Bridge condition
  • Integration with logistics and industrial development
  • Continuous public and expert advocacy

REALISTIC IMPLEMENTATION MODEL

PHASE I – URBAN BRIDGE

  • New bridge crossing over Varna Lake
  • Integration with urban road network
  • Traffic relief for southern districts
  • Backup transport link for emergencies
  • Estimated investment: €120–180 million
  • Timeline: 36–48 months after approvals

PHASE II – CONNECTING INFRASTRUCTURE

  • Feeder boulevards
  • Road interchanges
  • Motorway connections
  • Smart traffic systems
  • Estimated investment: €80–150 million

PHASE III – FULL TWO-LEVEL / LOGISTICS MODEL

  • Second bridge level
  • High-capacity transport corridor
  • Port and logistics integration
  • Deep-water port connectivity
  • Estimated investment: €600–900 million

PROJECT READINESS

  • Concept developed
  • Visual materials available
  • Preliminary investment framework
  • Expert analyses completed
  • Institutional initiatives conducted

Next required steps:

  • Pre-feasibility study
  • Option analysis
  • Traffic modeling
  • Geotechnical studies
  • Seismic assessment
  • Environmental assessment (EIA)
  • Technical design
  • Cost-benefit analysis (CBA)
  • Financial structuring
  • EU funding application

FINANCING STRUCTURE

  • CEF Transport
  • Transport Connectivity Programme
  • ERDF / Cohesion Fund
  • European Investment Bank
  • InvestEU
  • State co-financing
  • Municipal participation
  • PPP for complementary components

FINANCIAL MODEL (EXCEL LOGIC)

INPUT PARAMETERS

  • CAPEX Phase I: €120–180M
  • Total CAPEX: €600–900M
  • Grant component: 50–85%
  • Project lifetime: 40–60 years

ECONOMIC LOGIC

  • Travel time savings
  • Reduced congestion
  • Lower transport costs
  • Risk mitigation
  • Improved network reliability
  • Increased investment attractiveness

IRR / ROI

  • Economic IRR: 5–9%
  • Social ROI: High
  • Financial IRR: Low without tolls
  • Public funding recommended

CONSOLIDATED EXPERT CONCLUSION

The project represents a strategic infrastructure priority for Varna, the region, and the national economy. The second bridge is essential for ensuring redundancy, safety, economic development, and long-term transport sustainability.

The professional and realistic approach is phased implementation, starting with a functional urban bridge, followed by gradual expansion into a full two-level system based on demand, funding, and institutional readiness.

The BSEZ Cluster has fulfilled its role by developing the concept and initiating institutional dialogue. The next step is formal adoption, technical development, and submission for European and national funding.

„In order to optimize the transport infrastructure and traffic in the region, the construction of a new second bridge to the existing Asparuhov Bridge in the project“ Second Asparuhov Bridge on two levels“ is proposed according to the approved route for the second bridge under the current General Development Plan – Varna. The construction of a second bridge is an important transport project of the city of Varna, which will allow the complete removal of the transit traffic from the Hemus and Black Sea highways via the new cable bridge and will significantly reduce the urban traffic through the city. It is planned for the bridge to be built on two levels (two-stage implementation): Level 2 – for traffic from the city and from Levski Blvd. and Level 1 – for the traffic from the “Hemus” and “Black Sea” highways.“

  • DATE: March 2017 / Updated expert framework: 2026
  • INITIATOR / CONCEPT DEVELOPER:
    Black Sea Economic Zone Cluster (BSEZ Cluster)
  • INSTITUTIONAL FRAMEWORK / POTENTIAL PARTNERS:
    Regional Administration – Varna, Ministry of Regional Development and Public Works (MRDPW), Municipality of Varna, and relevant state authorities
  • IMPLEMENTATION TIMELINE:
    Up to 6 years following secured financing, selected project option, approved technical design, Environmental Impact Assessment (EIA), and permitting procedures
  • INITIAL INVESTMENT FRAMEWORK:
    Approx. €0.7 billion for Phase I (Level 1) / approx. €0.9 billion for full Phase I & II development (Levels 1 and 2)
  • UPDATED REALISTIC MODEL:
    Phased implementation – initial urban bridge connection and feeder infrastructure, followed by potential full development of a two-level / high-capacity structure
  • INITIAL ECONOMIC ESTIMATE:
    ROI above 5.5% under full project scenario with validated transport, logistics, and economic benefits
  • PROJECT READINESS:
    Developed concept, visual materials, preliminary investment framework, and justification for European financing available within BSEZ Cluster (conceptual / pre-investment phase)
  • POTENTIAL FUNDING SOURCES:
    European programmes and instruments, CEF Transport, Transport Connectivity Programme, ERDF, European Investment Bank (EIB), state funding, and blended financing models subject to eligibility and institutional support

OFFICIAL EXPERT OPINION
European Funding Experts – Brussels

Regarding the project “Second Asparuhov Bridge – Two-Level Structure – Varna”

I. SUBJECT OF THE OPINION

This expert opinion examines the project “Second Asparuhov Bridge – Two-Level Structure – Varna”, developed and proposed by the Black Sea Economic Zone Cluster (BSEZ Cluster), as a strategic transport, urban, port-related and regional infrastructure concept. The project envisages the construction of a new bridge connection over Varna Lake along a corridor included in the Master Plan of Varna, with two main functions: an urban alternative to the existing Asparuhov Bridge and the possibility to divert transit and motorway traffic towards Hemus Motorway and Black Sea Motorway. In the project materials of BSEZ Cluster, the concept is developed as a two-level bridge – one level for urban traffic and one level for transit/motorway traffic, with the possibility of phased implementation.

II. BASIS AND RELEVANCE

Since 2013, the second bridge corridor has been included in the Master Plan of Varna as a strategic infrastructure facility. More than ten years later, there is still no real institutional progress corresponding to the scale of the problem. At present:

  • there is no decision of the Varna Municipal Council for project implementation;
  • no pre-feasibility study has been commissioned;
  • there is no official traffic model;
  • no cost-benefit analysis (CBA) has been prepared;
  • there is no technical design;
  • no application for European funding has been submitted;
  • the project has not been included in a national infrastructure pipeline;
  • there is no institutional launch of the project.

The factual conclusion is that the project is planned within the spatial development framework of the city, but has not been institutionally initiated.

III. ACTIVITIES OF BSEZ CLUSTER – ACTIONS ACTUALLY UNDERTAKEN

BSEZ Cluster is the organisation that has systematically developed the issue of a second bridge as a strategic project for Varna. The actions undertaken include:

  • development of a conceptual design for a two-level bridge;
  • development of alternative options: bridge, lock, terminal and combined solutions;
  • preparation of technical parameters and visualisations;
  • alignment of the proposed corridor with the Master Plan of Varna;
  • development of a concept separating urban and transit traffic on different levels;
  • organisation of a working meeting at the Ministry of Regional Development and Public Works in 2019 with the participation of European funding experts from Brussels;
  • civil-expert survey of the existing Asparuhov Bridge;
  • creation of a public visual analysis and information platform: http://www.asparuhovmost.com/;
  • continuous public advocacy and expert positioning of the project;
  • linking the project with European transport, port and logistics corridors;
  • positioning the project within the broader development framework of Varna and North-Eastern Bulgaria.

IV. SURVEY OF ASPARUHOV BRIDGE AND RELEVANCE TO THE PROJECT

BSEZ Cluster carried out a civil-expert survey of Asparuhov Bridge in 2018–2019. The survey raised concerns regarding several serious deficiencies in the maintenance and monitoring of the structure, including:

  • absence of an updated seismic assessment;
  • absence of systematic geodetic monitoring of structural deformations since 1999;
  • non-operational inspection/service platforms;
  • unmaintained roller bearings;
  • corrosion and defects affecting structural elements;
  • corrosion beneath pedestrian walkways;
  • lack of inspection of key structural components for decades;
  • friction bolts not inspected since 2000.

The expert conclusion is that Asparuhov Bridge is critical infrastructure with increased systemic risk and without an equivalent reserve alternative.

V. WHAT HAS BEEN DONE BY THE INSTITUTIONS

Municipality of Varna:

  • no pre-feasibility study has been commissioned;
  • no public procurement procedure for technical design has been launched;
  • no updated traffic analysis has been prepared;
  • no CBA has been prepared;
  • no project package for EU funding has been prepared;
  • no publicly presented implementation roadmap exists.

Varna Municipal Council:

  • no decision has been adopted to initiate implementation of the second bridge;
  • no procedure has been assigned to the Mayor for commissioning a pre-feasibility study;
  • no phased development programme has been adopted;
  • no decision has been made to classify the project as a priority municipal infrastructure project;
  • no institutionally traceable initiative for European funding has been undertaken.

Ministry of Regional Development and Public Works:

  • a working meeting was held in 2019 at the initiative of BSEZ Cluster;
  • there is no publicly traceable inclusion of the project in a national infrastructure pipeline;
  • there is no state strategy for implementation;
  • there is no publicly announced follow-up procedure for technical studies, CBA, EIA or funding application.

VI. KEY PROBLEM – INSTITUTIONAL DELAY

Since 2013, the project has existed as a corridor in the Master Plan of Varna. There is a concept developed by BSEZ Cluster, public and expert justification, a meeting held at the Ministry of Regional Development and Public Works, a civil-expert survey of Asparuhov Bridge and a publicly stated problem concerning the absence of a reserve transport connection.

However, there is no decision of the Varna Municipal Council, no commissioning of a pre-feasibility study, no real project launch, no technical design, no European funding application and no state-level structuring.

The conclusion is that Varna Municipal Council and the Municipality of Varna have delayed the development of the project for more than ten years through the absence of decision-making, commissioning and consistent institutional action.

VII. BSEZ CLUSTER PROPOSAL – PHASED MODEL

BSEZ Cluster does not propose a one-off mega-project implementation, but a realistic phased approach, allowing the project to progress in a practical, financially manageable and EU-compliant manner.

Stage 1 – Critical urban stage:

  • new urban bridge connection;
  • provision of an alternative to Asparuhov Bridge;
  • possibility for major rehabilitation of the existing bridge without blocking the city;
  • traffic relief for the southern districts;
  • improved safety and redundancy of the transport system.

Stage 2 – Transit and motorway stage:

  • diversion of transit traffic;
  • connection to Hemus Motorway;
  • connection to Black Sea Motorway;
  • development of feeder infrastructure;
  • intelligent traffic management.

Stage 3 – Logistics and regional stage:

  • integration with port logistics;
  • connection to industrial zones;
  • development of intermodal and terminal components;
  • linkage with deep-water development of Port Varna;
  • integration into a regional logistics corridor towards Central Europe.

VIII. TECHNICAL AND TRANSPORT FRAMEWORK

In the available materials, BSEZ Cluster examines several engineering solutions: raising the existing Asparuhov Bridge, constructing a new two-level bridge, developing a second cable-stayed bridge, building a new lock-dock chamber, and applying a combined “bridge & lock & terminal” model. The new two-level bridge concept is described with an approximate length of 1,900 m, width of 29 m, two dual carriageways, capacity for both motorway and urban traffic, a main bridge section of approximately 798 m, and maximum clearance above water of 57.91 m.

IX. FINANCIAL MODEL – EXPERT FRAMEWORK / EXCEL LOGIC

Investment – realistic ranges:

  • Stage 1: €120–180 million;
  • Stage 2: €200–330 million;
  • full model: €600–900 million.

Financing:

  • EU programmes – CEF, Transport Connectivity Programme, Cohesion Fund;
  • state co-financing;
  • municipal participation for feeder infrastructure;
  • European Investment Bank / InvestEU;
  • PPP only for complementary components.

Return logic:

  • Economic IRR: approximately 5–9%;
  • social return: high;
  • Financial IRR: low or negative without direct tolling;
  • private ROI: mainly applicable to logistics, terminal and commercial zones.

X. EU FUNDING STRUCTURE AND EUROPEAN PRACTICE

The realistic model for EU funding is phased:

  • Stage 1: application for pre-feasibility study, option analysis, CBA, EIA, technical design and financial model;
  • Stage 2: inclusion in a national project pipeline and coordination with MRDPW, Ministry of Transport, Road Infrastructure Agency, Municipality of Varna, Regional Administration and port institutions;
  • Stage 3: application for construction financing under CEF Transport, Transport Connectivity Programme, ERDF/Cohesion Fund or a blended financing model with EIB;
  • Stage 4: state/municipal co-financing and potential PPP for complementary components.

XI. KEY CONCLUSION AND IMMEDIATE RECOMMENDATIONS

The project proposed by BSEZ Cluster is technically justified, strategically necessary, included in the Master Plan, socially significant, aligned with European practice, based on a phased implementation model and suitable for European funding logic.

The core problem is not the project itself, but the lack of institutional decision-making and action.

The immediate necessary steps are:

  • decision of Varna Municipal Council to initiate project preparation;
  • commissioning of a pre-feasibility study by the Mayor;
  • preparation of a CBA and traffic model;
  • official option analysis;
  • structural, geodetic and seismic survey of Asparuhov Bridge;
  • inclusion in a national infrastructure pipeline;
  • preparation for EU funding;
  • institutional working group involving MRDPW, Ministry of Transport, Road Infrastructure Agency, Municipality of Varna, Regional Administration and BSEZ Cluster.

XII. CONCLUSION

The project “Second Asparuhov Bridge – Two-Level Structure – Varna” is a strategically significant concept with high public, transport and regional value. BSEZ Cluster has fulfilled its role: it has formulated the problem, proposed a solution, developed a technical concept, prepared alternative options, conducted a civil-expert survey of Asparuhov Bridge and initiated institutional dialogue, including a working meeting at the Ministry of Regional Development and Public Works with the participation of experts from Brussels.

In precise terms: BSEZ Cluster has already completed the civil-expert work related to problem definition, concept development and strategic logic. The next necessary step is for the Municipality of Varna, Varna Municipal Council and the state to initiate a real implementation procedure through an official pre-feasibility study, option analysis, CBA, EIA, financial model and application for European funding.

MISSED FUNDING OPPORTUNITIES UNTIL 2027 AND INSTITUTIONAL DELAY – EXPERT LEGAL AND PROCEDURAL ASSESSMENT

Based on a review of available project materials, public sources, official correspondence, and applicable European Union regulatory frameworks, it is established that the project “Second Asparuhov Bridge – Two-Level Structure – Varna” has not passed the mandatory preparatory stages required for eligibility under European funding programmes for the 2021–2027 period.

The expert assessment is unequivocal: the reason is not the lack of a concept, but the absence of formal institutional decision-making and assignment, despite the existence of systematic initiatives, expert developments, and official proposals by the BSEZ Cluster [1].

According to European practice, from the very beginning of the 2021–2027 programming period there was a clear opportunity for the project to be structured through:

  • – pre-feasibility study
  • – option analysis
  • – traffic modelling
  • – CBA (cost-benefit analysis)
  • – EIA / environmental assessment
  • – conceptual or technical design
  • – JASPERS technical assistance

These activities are standard EU-funded components and represent a mandatory prerequisite for subsequent investment financing.

DOCUMENTED INSTITUTIONAL INITIATIVE (BSEZ CLUSTER)

The available documentation confirms that BSEZ Cluster has undertaken formal actions, including:

  • – Letter No. OS24000111VN / 14.02.2024 to Mayor Blagomir Kotsev and Chairman of Varna Municipal Council Hristo Dimitrov
  • – Letter No. 20240001003 / 14.02.2024 to Mayor Blagomir Kotsev and Chairman of Varna Municipal Council Hristo Dimitrov
  • – Letter RD-24-9407-69 / 10.10.2024 to the Regional Governor of Varna
  • – Follow-up letter RD-24-9407-69 / 28.10.2024 to Mayor Blagomir Kotsev

These communications proposed the establishment of a working group, commissioning of a pre-feasibility study, and preparation for European funding [2].

Additionally, in 2019, a working meeting was held at the Ministry of Regional Development and Public Works with participation of experts from Brussels [3].

EXPERT FINDINGS

  • – absence of a decision by Varna Municipal Council
  • – absence of commissioned pre-feasibility study
  • – absence of traffic model
  • – absence of CBA analysis
  • – absence of environmental assessment (EIA)
  • – absence of technical design
  • – absence of application for EU funding

This constitutes a direct deviation from standard European project development logic.

LEGAL CONCLUSION

Under Bulgarian spatial planning law, environmental legislation, and EU funding regulations, a project lacking preparatory studies and a formal contracting authority cannot be considered eligible for financing.

COUNTERFACTUAL SCENARIO

Had a decision been taken after 2013 or following BSEZ Cluster proposals in 2024, by 2026 Varna could have had:

  • – completed pre-feasibility study
  • – option analysis
  • – traffic model
  • – CBA analysis
  • – environmental assessment
  • – conceptual design
  • – readiness for EU funding application

CURRENT STATUS (2026)

At present, only preparatory-phase funding remains realistically accessible. Full construction financing before 2027 is not feasible.

Realistic horizon for implementation: 2028–2034.

DEFINITIVE EXPERT CONCLUSION

  • – the project has been included in the Master Plan of Varna since 2013
  • – it has been developed by BSEZ Cluster
  • – institutional initiatives exist
  • – decision-making and formal assignment are missing

The delay is entirely institutional.

FINAL CONCLUSION

BSEZ Cluster has fulfilled its expert role. The missing element is institutional action. Immediate initiation of a formal pre-investment preparation procedure is required.

PUBLIC SOURCES

[1] https://bsezcluster.org/2025/11/28/pozicia/
[2] https://bsezcluster.org/2024/02/14/%d0%b3%d1%80%d1%83%d0%bf%d0%b0/
[3] https://bsezcluster.org/2019/05/20/mrrb/
[4] https://bsezcluster.org/2018/08/13/ob/